Friday 30 November 2012

Le Mazot - work in progress...

It's been 2 months since our first post about Le Mazot and things have changed - and not just the weather.    

We've filled in the old hole for the chimney and installed a new one. Which involved pouring a concrete pad that slopped and didn't drop onto the floor below, cutting new shingle tiles and making sure the new copper work was straight. A first and no one fell off despite the snow..

Inside we've installed a new floor, drains and made a new wall...

plus this week we've finished insulating the ceiling and have put up the new panelling...


We're still awaiting our planning permissions, but all being well we should get that in the next week and be able to start on the windows and walls